At the October 2 clean-energy roundtable in Brussels, EU and Azerbaijani officials invited European companies to invest in electricity corridors not crossing Russia, in particular those connecting South Caucasus renewable generation to European markets. Energy Commissioner Dan Jørgensen identified European equipment, engineering, and investment as contributions to Azerbaijan’s planned interconnections.[1]
The Georgia–Romania interconnector forms the maritime link within the green-energy partnership among Azerbaijan, Georgia, Romania, and Hungary. The studied 1,300-megawatt configuration would add a source of renewable supply to European markets and an export route for producers east of the Black Sea.[2]
The EU’s regional strategy connects these electricity links to decarbonization and closer energy-market integration.[3] Realizing those objectives requires trading rules and transmission access that allow producers to sell across borders: the physical connection alone cannot establish an integrated market.
For the EU, the strategic case for the cable is that it would extend access to renewable supply beyond the Union’s borders while making European market rules and investment institutions more consequential in the South Caucasus. A prospective European contribution would help European companies assess how much expenditure public funds would cover and how much the project would need to recover through revenues.
For Azerbaijan, access to European electricity markets would give new renewable generation an export outlet and could help attract the investment needed to develop it. Azerbaijan’s wind and solar expansion already involves foreign and private companies, and its officials presented the next phase of corridor development as attracting investors and strategic partners. For European participants, the commercial question is whether generation and export infrastructure will develop on schedules that permit the resulting electricity to reach their intended markets.
The Georgia–Romania interconnector can now apply for EU grants under its Project of Mutual Interest designation. The second Union list was published in April 2026, providing listed projects with streamlined permitting and regulatory support as well as eligibility for Connecting Europe Facility finance.[4] The 2026 CEF Energy call offered €600 million for studies and works across eligible projects and closed on September 30.[5] Eligibility establishes a route to European support without specifying how much the Union will contribute.
“The EU should define its prospective financial contribution while the cable’s sponsors complete the work needed for an investment decision.”
World Bank support is financing the preparatory studies from which the sponsors must develop a construction-financing proposal. The Bank approved a $35 million loan for the first phase of Georgia’s ESPIRE program in 2024. Its possible later phases would strengthen onshore transmission and support cable construction, subject to decisions to proceed and the availability of financing.[6]
The Bank’s February mission placed a possible request to the EU for a construction grant in a later application cycle, once the project was sufficiently developed. The mission also required updated market and financial assessments and decisions about ownership.[7] These questions are connected: projected trading revenues inform the financing requirement, while ownership determines who assumes the investment obligations.
The feasibility study distinguishes the cable’s wider economic benefits from the revenues available to repay its investors. Its 2024 financial model requires grants covering at least 20 percent of financing, most debt supplied by international financial institutions, and equity returns consistent with public investors’ expectations. These are model conditions rather than a definitive subsidy formula for the eventual project.[8]
Under different ownership models, grants would improve investor returns or reduce costs recovered through transmission tariffs. The justification for a European contribution therefore rests partly on decarbonization, diversification, and market-integration benefits that the interconnector cannot fully recover through its own revenues.
The Commission should agree with the participating governments and lenders how much EU grant support is needed to make the cable financeable. That commitment should specify which costs European funds would cover and what the project’s sponsors must complete before the money is released.
The sponsors’ updated business model should establish how alternative grant contributions would affect borrowing requirements and the costs recovered through transmission tariffs. Lenders and national regulators could then assess the financing proposal against the same assumptions. The EU’s connectivity platform, launched in June, gives the Commission a forum for securing agreement among these institutions.[9]
The sponsors should coordinate the cable’s investment schedule with the renewable projects expected to supply electricity for export. Installed capacity targets do not establish how much electricity will be available after domestic consumption, or when it can be delivered. The feasibility study models electricity exchanges under different generation and demand assumptions. Export availability when the cable enters service will depend on generation completed by then, electricity retained for domestic consumption, and the capacity of the Azerbaijani and Georgian networks to transmit the remainder.
“The cable’s European value depends on renewable electricity reaching buyers through the grids connected to both ends of the crossing.”
The investment required on the Romanian side depends on the network’s capacity both to receive the cable’s imports and to transmit them onward into European markets. Transelectrica’s July workshop examined the route and authorization of the Romanian section, along with the investments needed to integrate 1,300 megawatts in the Constanța area.
Any investment in the Romanian network for receiving and transmitting the cable’s imports must enter the corridor’s financing plan. Otherwise, the cost of the sea crossing would provide an incomplete basis for judging the investment needed to bring the imports to European buyers.
European coordination should help the project’s sponsors resolve survey permissions involving Bulgaria and Türkiye before delays raise the cost of preparing the cable. The World Bank warned that delayed permissions could leave survey vessels idle or require their withdrawal and remobilization, adding costs before construction begins.
Securing those permissions before committing vessels would limit that exposure. Procurement must also accommodate the specialized manufacturing and installation capabilities identified in the feasibility study, so the sponsors face distinct constraints on survey mobilization and subsequent construction contracting.
A prospective Caspian connection would broaden the renewable supply available to Europe, provided the Black Sea connection and the intervening grids can carry it. On October 9, Azerbaijan announced a $1 million grant for development of the Caspian Green Energy Corridor linking Azerbaijan, Kazakhstan, and Uzbekistan, funded through the Multilateral Cooperation Center for Development Finance and administered by AIIB.[10]
This is support for preparation, not construction of the crossing. For Europe, the prospective Caspian supply reinforces the need to assess Black Sea capacity together with the intervening transmission requirements, before separate investment decisions constrain the corridor’s eventual use.
The remaining studies must establish the cable’s financing requirements, but the sponsors also need an indication of European support to develop a credible business model. A conditional commitment would give the sponsors a basis for structuring the investment while leaving disbursement dependent on substantiating the benefits claimed for European support.
The Commission should specify the EU’s proposed financial contribution and the conditions for releasing it, so that the sponsors can take an investment decision.
REFERENCES
[1] Ministry of Energy of Azerbaijan, “Azerbaijan-EU Clean Energy Roundtable Was Held in Brussels,” October 2, 2026, https://minenergy.gov.az/en/xeberler-arxivi/00901
[2] Transelectrica, Consolidated Half-Yearly Report H1 2026 (2026), discussion of the July 29 Black Sea cable workshop, https://www.transelectrica.ro/documents/10179/23486255/Consolidated%2B1H%2BReport.pdf/3679da03-a574-42e3-8499-24d878ff2820
[3] European Commission and High Representative of the Union for Foreign Affairs and Security Policy, The European Union’s Strategic Approach to the Black Sea Region (May 2025), https://enlargement.ec.europa.eu/document/download/170d9b3a-d45f-4169-80fa-9adb753c0921_en
[4] European Commission, “235 Key Cross-Border Energy Projects to Boost Europe’s Interconnectivity,” April 9, 2026, https://energy.ec.europa.eu/news/235-key-cross-border-energy-projects-boost-europes-interconnectivity-2026-04-09_en
[5] European Climate, Infrastructure and Environment Executive Agency (CINEA), “CEF Energy Launches €600 Million Call for Energy Infrastructure Projects,” April 30, 2026, https://cinea.ec.europa.eu/news-events/news/cef-energy-launches-eu600-million-call-energy-infrastructure-projects-2026-04-30_en
[6] World Bank, “World Bank Approves $35 Million Investment for Black Sea Submarine Cable Project Preparatory Activities,” May 21, 2024, https://www.worldbank.org/en/news/press-release/2024/05/21/world-bank-approves-35-million-investment-for-black-sea-submarine-cable-project-preparatory-activities
[7] World Bank, Georgia—Implementation Support Mission: Enhancing Energy Security through Electricity Interconnection and Renewable Energy (ESPIRE) Phase 1 Project, aide-mémoire, February 17–20, 2026, https://documents1.worldbank.org/curated/en/099041426055014514/pdf/P179950-99b07206-8620-440e-94b6-3cd887995526.pdf
[8] Georgia–Romania Black Sea Submarine Cable Project Feasibility Study Summary, summary of the CESI feasibility study completed in July 2024, https://www.maritime.bg/wp-content/uploads/2024/11/Black_Sea_Submarine_Cable_Project_Feasibility_Study_Summary-.pdf
[9] European Commission and High Representative of the Union for Foreign Affairs and Security Policy, Joint Report to the European Parliament and the Council on the Implementation of the EU Strategic Approach to the Black Sea Region, JOIN(2026) 15 final, July 3, 2026, https://enlargement.ec.europa.eu/document/download/06e341ed-8e59-4d3f-b2bd-083b0b5a9027_en
[10] Ministry of Energy of Azerbaijan, “Grant Agreements Were Signed with AIIB for Green Energy Projects in Azerbaijan,” October 9, 2026, https://minenergy.gov.az/en/xeberler-arxivi/00909